Return to CBFWA Homepage
   

FY 2007-2009 BPA Fish & Wildlife Program Budget Tracking Process

Document approved October 31, 2006

Project Level Start Of Year (SOY) Budget

  1. NPCC SOY - the Council approves a Start of Year Budget that includes planned expense and capital projects. When this Program budget is adopted, it resolves all pending within year budget adjustments for the previous fiscal year. Any future modifications to project budgets must submit a Project Modification Request Form as described in this document.
  2. BPA SOY - BPA will use the Council recommendations to create the BPA SOY Budget. After refining the Council SOY budget for any errors, omissions, or changes, the BPA SOY Budget will be created. The BPA SOY budget will not change once adopted and will be used as the basis for the BPA Working Budget. The BPA working budget will change throughout the FY to reflect changes made to project budgets as determined through the budget modification process described below. The working budget comprises spending plans, the project level non-contract costs and any adjustments made throughout the year. A record will be kept of all modifications to project budgets.
  3. c. SOY tracking - BPA project budgets, variance reports, and spending will be available on their F&W Website under the fiscal information section. BPA will provide that information to CBFWA for placement on their website http://www.cbfwa.org/mods/ per the process outlined below.

Monthly Budget Oversight Group (BOG) - Tracking Project Budgets through the Fiscal Year

  1. The Budget Oversight Group (BOG) consists of Council state and central staff, BPA staff, CBFWA staff and others tasked with coordination functions.
  2. The BOG will meet monthly to review budget adjustment requests and to track the fiscal year budget.
    1. This meeting will be held on the Wednesday prior to regularly scheduled, current month's NPCC meetings.
    2. BPA COTRs and project sponsors should work together to ensure the appropriateness and accuracy of the project modification request. Project sponsors must attend BOG meetings either in person or via phone to discuss their requests. Otherwise, their requests will not be considered at that particular BOG meeting and will be deferred to the next BOG meeting. All project modification requests must be submitted no later than one week prior to the BOG meeting for consideration in that month.
    3. All requests received will be reviewed, sorted and categorized. A report of these actions will be posted monthly to the BOG web page on the CBFWA web site.
    4. The BOG meetings will be open to the public and announced on the CBFWA web site.
  3. BPA will provide a monthly budget-to-actuals report that will show all project budget adjustments during the Fiscal Year by province. BPA should report the reason for the budget adjustment for each project in its report. These reports will be updated monthly and are posted on the BPA web site.

Quarterly Review

The Quarterly Review meetings will occur near the beginning of each quarter at the regularly scheduled BOG meeting. The purpose of these meetings will be to provide the current FY status of contracting and spending for the Program. BPA will provide a summary of the Program budget to identify available funding for re-allocation. BPA will provide a complete list of current budget modification requests, with the BOG-assigned categories, to align the requests with the available funding.

BPA will initiate a prioritization process by holding meetings the first (January) and second (April) and third (July) quarterly reviews of the fiscal year to establish funding priorities for budget adjustment requests received during the fiscal year quarter.

The quarterly review process will include a 14-day public comment period.


Figure 1. Quarterly review process.

Project Modification Request Process

  1. Project sponsors can request modifications to their projects by submitting a project modification request form (available on CBFWA website). There are three possible adjustments for ongoing projects: (1) scope change, (2) budget change, and (3) scope/budget change. Moving from one step to another in the Three-Step Review Process is considered a scope and budget change. Project sponsors can also request a Reschedule or New Start project using the funding request form.
    1. All project modification requests must be submitted through the CBFWA web site for consideration by the BOG.
  2. All requests will be tracked and received via the BOG web page; a copy of those requests, including the BOG agendas and supporting material, will be forwarded to the BOG members.
  3. The BOG members will determine whether the request is (1) a request for a Scope change; (2) a request for a Budget Adjustment (either rescheduled work or additional work within scope); or (3) a request for a Budget Adjustment and Scope change (includes new proposals) and place the requests into the appropriate categories (see Figure 2).
    1. Depending on the circumstances, category 1 and category 3a projects may be forwarded to the BOG Management Group for action (this group is made up of the F&W Directors for Council, BPA and CBFWA). The BOG Management Group may forward requests directly to Council for decision or return to the BOG for consideration at the Quarterly Review. Depending on sequence to the next Council meeting, these requests will be addressed as quickly as possible.
    2. Reschedules are forwarded to BPA. As part of the reschedule request, BPA and the sponsor will provide a written account identifying the following two items: 1) confirmation of money available in the project budget to cover the rescheduled tasks, 2) a timeline for expected task completion. BPA will have the discretion to make necessary project budget modifications that are determined to be reschedules. BPA-denied requests will be sent back to the BOG for categorization.
    3. All other requests will be reviewed by the BOG and placed into the appropriate adjustment categories. Scope Change and New Requests (e.g., ESA needs) may need to have ISRP and CBFWA reviews.
  4. Recommendations regarding any action will be updated monthly at BOG meetings and provided to Council staff one week prior to packet day.
  5. For actions deemed “Emergency” by the BOG-Council, BPA and CBFWA staffs will seek a recommendation from the BOG Management Group and present the requests to the Council’s Fish and Wildlife Committee for recommendation to the full Council at the same meeting. The Council will then make a recommendation to BPA regarding funding the requests.
  6. All other actions (i.e., scope changes and new requests), after completing the necessary reviews as part of the quarterly review, will be presented to the Council’s Fish and Wildlife Committee for recommendation to the full Council at the next Council meeting. The Council will then make a recommendation to BPA regarding funding the requests.


Figure 2. Within-Year Budget Modification Process.

Budget Adjustment Prioritization Criteria

AWithin-Year project modification requests (not reschedules) will be placed into one or more of the following categories by the BOG:

    Adjustment Categories

  1. Emergency – Acts of God or the unforeseen loss of mechanical infrastructure that necessitates an extraordinary action to avoid the imminent loss of fish and/or wildlife resources or to mitigate serious human health or safety issues.
  2. ESA Obligation – A new or ongoing project that addresses actions committed to by the Action Agencies to implement biological opinions. New projects will be reviewed by the
  3. Threats to Project Integrity – Actions necessary for the project, though not of an emergency nature, to avoid the loss of a previous project investment, including major project review (i.e., step review) that would:
    1. Jeopardize the performance of the entire project
    2. Jeopardize the performance of a discrete task or objective of the project causing:
      1. adverse biological consequences to the project;
      2. the loss of monitoring and evaluation data.
  4. Lost Opportunity – New or ongoing projects that respond to a limited opportunity to benefit the fish and wildlife resource and that opportunity will be permanently lost if the requested budget increase and associated work is not approved. “Lost opportunity”constitutes a highly scrutinized status and does not necessarily constitute an automatic approval.
  5. Other – Any project not deemed by the BOG to fall into the four categories defined above. The loss of capability to administer the project also falls into this category. Examples of this type of request might include cost-of-living increases or increases in indirect rates. Because these costs should be addressed through project contracting, it is unlikely that these projects would receive a high priority in the quarterly review process.

New Start Projects

New projects will be reviewed by the Independent Scientific Review Panel, BPA and the Council prior to BPA funding.

Glossary

Budget Oversight Group Meetings Currently Scheduled:

Meeting Date Submission Deadline
for this Meeting
June 4, 2008 May 28, 2008
July 9, 2008 July 2, 2008
August 6, 2008 July 30, 2008
September 10, 2008 September 3, 2008
October 8, 2008 October 1, 2008
November 12, 2008 November 5, 2008
December 3, 2008 November 26, 2008

Example of Project Modification Request Timeline

Date Day of action Action
Oct 20 1 Submit Request to COTR for review
Oct 27 7 COTR review and return to Sponsor
Nov 3 14 Last Day to Submit Request to CBFWA Website
Nov 10 21 BOG review
Dec 14 48 Request presented to F&W Committee (if needed)
Jan 12 77 Request presented to Full Council (if needed)

 

 

Maintained by the Columbia Basin Fish & Wildlife Authority. Please direct comments or questions to the webmaster.