| Work Element Name |
Work Element Title |
Description |
Start Date |
End Date |
Estimated Budget |
| 01: Produce Environmental Compliance Documentation |
WE 1: NEPA Analysis and Documentation |
Insure all applicable compliance documentation are submitted for permits, and a completed NEPA checklist will be submitted to obtain signoff from the BPA Environmental Compliance group prior to project implementation |
5/1/2007 |
4/30/2010 |
$12,810 |
| Biological Objectives |
Metrics |
1. Implement habitat restoration and enhancement p
|
No Metrics for this Work Element |
|
| 02: Analyze/Interpret Data |
WE 2: Assess Large Woody Debris Recruitment Potential in target Watersheds |
Evaluate the LWD recruitment in potential 2nd order tributaries within the Hangman Creek watershed. Revise performance standards for LWD volume/frequency and identify and prioritize sites for restoration treatment. |
5/1/2007 |
4/30/2008 |
$9,506 |
| Biological Objectives |
Metrics |
1. Implement habitat restoration and enhancement p
|
Focal Area: 20 miles
|
|
| 03: Identify and Select Projects |
WE 3: Identify and Select New Restoration Projects |
Engage in advanced scoping of restoration projects with private landowners in the Hangman Watershed. Make contacts with landowners, negotiate agreements, and conduct field evaluations to characterize baseline conditions on properties where projects are likely to occur. |
5/1/2007 |
4/30/2010 |
$23,598 |
| Biological Objectives |
Metrics |
1. Implement habitat restoration and enhancement p
|
No Metrics for this Work Element |
|
| 04: Produce Plan |
WE 4: Produce Design of Hangman Creek Assessment and Restoration Prescriptions. |
Will contract out to Inter-Fluve Inc, to have a 4.0 mile section of Hangman Creek (from the confluence of Indian to the confluence of Nehchen Creek) evaluated for existing channel and flodplain conditions, and a conceptual design of restoration prescriptions provided. |
5/1/2007 |
4/30/2008 |
$50,279 |
| Biological Objectives |
Metrics |
1. Implement habitat restoration and enhancement p
|
No Metrics for this Work Element |
|
| 05: Produce Design and/or Specifications |
WE 5: Produce Site Specific Restoration Designs for major channel realignment |
Produce a 30%level of design needed for fit in the field construction to restore stable channel plan, profile and dimension to approximately 1.3 miles of channel in the mainstem of Hangman Creek below the Indian Creek confluence. This will involve two separate properties still under negotiation. |
5/1/2007 |
4/30/2009 |
$110,380 |
| Biological Objectives |
Metrics |
1. Implement habitat restoration and enhancement p
|
No Metrics for this Work Element |
|
| 06: Produce Design and/or Specifications |
WE 6: Produce Design for Minor Restoration Projects |
In-house designs for LWD placement, riparian fencing, and riparian enhancement projects. |
5/1/2007 |
4/30/2010 |
$33,104 |
| Biological Objectives |
Metrics |
1. Implement habitat restoration and enhancement p
|
No Metrics for this Work Element |
|
| 07: Realign, Connect, and/or Create Channel |
WE 7: Major channel reconstruction and realignment |
Implement channel restoration design (WE 5) for mainstem Hangman Creek to recover abandoned channel alignment and raise the invert of existing channel segments to near historical elevations per design specifications. Anticipated that 2 separate properties and two separate projects will be involved with this work element. |
5/1/2008 |
10/30/2009 |
$437,568 |
| Biological Objectives |
Metrics |
1. Implement habitat restoration and enhancement p
|
* # of stream miles treated, including off-channels, after realignment: 1.5 miles
|
|
| 08: Install Fence |
WE 8: Install fence to exclude cattle from fish-bearing stream |
Install 1.0 mile of fence on the Damon property on Sheep Creek to exclude cattle from riparian area, and armour banks where cattle are allowed access to stream for watering. |
5/1/2007 |
11/1/2007 |
$21,366 |
| Biological Objectives |
Metrics |
1. Implement habitat restoration and enhancement p
|
* # of miles of fence: 2.0 miles
|
|
| 09: Plant Vegetation |
WE 9: Plant Riparian Vegetation at Various Undetermined Sites |
Restore native riparian plant communities within the 100 year floodplain of streams within the Hangman watershed |
5/1/2007 |
4/30/2010 |
$146,991 |
| Biological Objectives |
Metrics |
1. Implement habitat restoration and enhancement p
|
* # of riparian miles treated: 3.0 miles
|
|
| 10: Increase Instream Habitat Complexity |
WE 10: Place Instream LWD in various tributary locations |
Install LWD at two tributary locations for a total of 2000 ft.
All work done within forested fish-bearing streams with low impact equipment, or done by hand. |
5/1/2008 |
4/30/2010 |
$88,300 |
| Biological Objectives |
Metrics |
1. Implement habitat restoration and enhancement p
|
* # of stream miles treated: 0.4 miles
|
|
| 11: Maintain Vegetation |
WE 11: Maintain Plants at Various Undetermined Sites |
Protect and maintain riparian plants (WE 9) from competition from exotic, invasive species, and from herbivores such as beaver and other rodents, and ruminates such as deer and elk. Chicken wire and plastic wrapping, plastic cones, and matting is among the treatments used. |
5/1/2007 |
4/30/2010 |
$38,678 |
| Biological Objectives |
Metrics |
1. Implement habitat restoration and enhancement p
|
No Metrics for this Work Element |
|
| 13: Collect/Generate/Validate Field and Lab Data |
WE 12: Collect Physical Habitat and Water Quality Data |
Water Quality: Taking discharge, water samples for TSS and turb, discharge at water qulity sites, deploying continuous temperatue monitors. Physcial habitat: Rosgen channel surveying to obtain cross sections, longitudinal profiles, LWD counts, pebble counts, gradient, and canopy. |
5/1/2007 |
4/30/2010 |
$100,950 |
| Biological Objectives |
Metrics |
2. Evaluate habitat restoration at treatment sites
|
Primary R, M, and E Type: Action Effectiveness Research
|
|
| 14: Submit/Acquire Data |
WE 13: Transfer Data from Field Equipment |
Covers downloading of Hobo temp monitors using a laptop, GPS, continuous level loggers, Allegro datalogger, and digital pictures into a PC. |
5/1/2007 |
4/30/2010 |
$9,796 |
| Biological Objectives |
Metrics |
2. Evaluate habitat restoration at treatment sites 3. Detect changes in fish production, productivity
|
No Metrics for this Work Element |
|
| 15: Create/Manage/Maintain Database |
WE 14: Maintain Water Quality and Physical Habitat Database |
Maintain water quality and quantity, physical habitat, and temperature databases for all data categories to support data analysis for TSS and turbidity, discharge, D.O., channel geometry, longitudinal profile, cross section dimension, channel substrate, large woody debris, stream canopy, and air and water temperature. |
5/1/2007 |
4/30/2010 |
$61,587 |
| Biological Objectives |
Metrics |
2. Evaluate habitat restoration at treatment sites
|
No Metrics for this Work Element |
|
| 16: Analyze/Interpret Data |
WE 15: Analyze Water Quality and Physical Habitat |
Analyze data from physical habitat sampling at reference and treatment sites, at temperature monitoring sites, and at water quality and discharge sites within the watershed. |
5/1/2007 |
4/30/2010 |
$44,346 |
| Biological Objectives |
Metrics |
2. Evaluate habitat restoration at treatment sites
|
Primary R, M, and E Type: Action Effectiveness Research
|
|
| 17: Install Fish Monitoring Equipment |
WE 16: Install and Maintain Traps |
Install resistence board weir in the mainstem of Hangman Creek, and install upstream and downstream migrant traps in Indian Creek, Sheep Creek, Mission Creek, and Nehchen Creek |
5/1/2007 |
3/30/2010 |
$17,668 |
| Biological Objectives |
Metrics |
4. Measure productivity of the fluvial lifehistory
|
No Metrics for this Work Element |
|
| 18: Collect/Generate/Validate Field and Lab Data |
WE 17: Trap salmonids to determine migratory patterns |
Monitor movement of juvenile and adult salmonids in the mainstem and tributaries of Hangman Creek. Capture downstream migrating juveniles and upstream spawners in weir traps in 4 tributaries (See WE 17), and upstream migrants in the mainstem of Hangman using a Resistence board weir (WE 17). For all fish sampled, measure length (nearest mm), weight (nearest 0.1 g) and take scale samples from each fish. |
1/2/2008 |
4/30/2010 |
$33,734 |
| Biological Objectives |
Metrics |
2. Evaluate habitat restoration at treatment sites 3. Detect changes in fish production, productivity 4. Measure productivity of the fluvial lifehistory
|
No Metrics for this Work Element |
|
| 19: Collect/Generate/Validate Field and Lab Data |
WE 18: Sample Fish Electroshocking Equipment |
Sample fish from 30 sample sites per year using electrofishing backpacks to detect changes in distribution, populations, and to develop a juvenile-to-adult survival estimate. For all fish sampled, measure length (nearest mm), weight (nearest 0.1 g) and take scale samples from each fish. |
6/1/2007 |
8/30/2009 |
$50,729 |
| Biological Objectives |
Metrics |
2. Evaluate habitat restoration at treatment sites 3. Detect changes in fish production, productivity 4. Measure productivity of the fluvial lifehistory
|
Primary R, M, and E Type: Status and Trend Monitoring
|
|
| 20: Create/Manage/Maintain Database |
WE 19:Maintain Fisheries Database |
A database of all fish sampling using electroshocking and trapping methods will be maintained for abundance, population estimates, age classes, and migrant trapping. |
5/1/2007 |
4/30/2010 |
$16,822 |
| Biological Objectives |
Metrics |
2. Evaluate habitat restoration at treatment sites 3. Detect changes in fish production, productivity 4. Measure productivity of the fluvial lifehistory
|
No Metrics for this Work Element |
|
| 21: Disseminate Raw/Summary Data and Results |
WE 20: Summarize Water Quality, Physical habitat, and Fisheries using GIS |
This work element covers GIS applications used to summmarize data such as salmonid distribution, riparian vegetative types and densities, canopy, percent fines, useable salmonid habitat for rearing and spawning, and areas identified as priorities for restoration. |
5/1/2007 |
4/30/2010 |
$15,978 |
| Biological Objectives |
Metrics |
2. Evaluate habitat restoration at treatment sites 3. Detect changes in fish production, productivity 4. Measure productivity of the fluvial lifehistory
|
No Metrics for this Work Element |
|
| 22: Coordination |
WE 21: Coordinate Restoration Efforts with Stakeholders |
Coordinate and participate in a variety of forums with local stakeholdrs and managers to disseminate information about restoration efforts and allow for participation by interested parties |
5/1/2007 |
4/30/2010 |
$54,826 |
| Biological Objectives |
Metrics |
5. Increase cooperation and coordination
|
No Metrics for this Work Element |
|
| 23: Outreach and Education |
WE 22: Outreach and Education |
Participate in and develop an educational forum for the local community and surrounding areas regarding stream restoration opportunities on the reservation. |
5/1/2007 |
4/30/2010 |
$37,231 |
| Biological Objectives |
Metrics |
5. Increase cooperation and coordination
|
* # of general public reached: 500
|
|
| 24: Manage and Administer Projects |
WE 23: Manage and Administer Project |
Provide oversight of the project as needed. Respond to BPA as requested, providing financial, contractual, and administrative documents. Prepare FY-09 Statements of Work and Budgets. |
5/1/2007 |
4/30/2010 |
$329,438 |
| Biological Objectives |
Metrics |
1. Implement habitat restoration and enhancement p 2. Evaluate habitat restoration at treatment sites 3. Detect changes in fish production, productivity 4. Measure productivity of the fluvial lifehistory 5. Increase cooperation and coordination
|
No Metrics for this Work Element |
|
| 25: Produce Status Report |
WE 24: Produce Quarterly Reports via Pisces |
Prepare quarterly status reports against each mileston, indicating whether the milestone is green, yellow or red. Reports will be filled in on-line via Pisces. |
5/1/2007 |
4/30/2010 |
$26,438 |
| Biological Objectives |
Metrics |
1. Implement habitat restoration and enhancement p 2. Evaluate habitat restoration at treatment sites 3. Detect changes in fish production, productivity 4. Measure productivity of the fluvial lifehistory 5. Increase cooperation and coordination
|
No Metrics for this Work Element |
|
| 26: Produce Annual Report |
WE 25: Produce Annual Reports |
Produce annual reports that summarize work accomplished in the previous 12 months. |
5/1/2007 |
4/30/2010 |
$48,204 |
| Biological Objectives |
Metrics |
1. Implement habitat restoration and enhancement p 2. Evaluate habitat restoration at treatment sites 3. Detect changes in fish production, productivity 4. Measure productivity of the fluvial lifehistory 5. Increase cooperation and coordination
|
No Metrics for this Work Element |
|