Project Proposal Request for FY 2007 - FY 2009 Funding (Revised Summer 2006)

Proposal 200724300: Crab Creek Subbasin Plan 2007

Download this document in MS Word format
Open this document in PDF format

Table of Contents
Part 1. Administration and Budgeting
Section 1: General Administrative
Section 2: Project Location
Section 3: Project Species
Section 4: Past Accomplishments
Section 5: Relationship to Other Projects
Section 6: Biological Objectives
Section 7: Work Elements
Section 8: Budget
Section 9: Project Future
Section 10: Documents
Part 2. Reviews
Part 1 of 2. Administration and Budgeting
Section 1: General Administrative Information
Process Information:
Date Proposal Submitted & Finalized Status Form Generator
July 14, 2006 Finalized Patrick Verhey
DB Administrator's Note [Per conversation with Patrick Verhey on 3/17/2006, Itemized budget total should be $20,000 rather than $5,778. - DBA]

Proposal Type: New
Proposal Number: 200724300
Proposal Name: Crab Creek Subbasin Plan 2007
Agency, Institution or Organization: Washington Department of Fish and Wildlife (WDFW)
Short Description: Project will provide a more complete wildlife section (assessment, inventory, and management plan) and address key ISRP comments on the original Crab Creek Subbasin Plan.The goal of the project is the adoption of the Crab Creek Subbasin Plan by the NWPCC.
Information Transfer: The information will be used to update the current Crab Creek Subbasin Plan in order for the plan to be adopted by NWPCC. The Crab Creek Subbasin Plan will be used to prioritize projects that lead to the recovery of ESA listed species. ESA listed species within the subbasin include Steelhead, Sharp-tailed Grouse, Sage Grouse, and Pygmy Rabbits. The plan will be posted on the NWPCC internet site.
 
Project Proposal Contacts
Contact Organization Address Phone/Email Roles Notes
Form Submitter
Patrick Verhey WDFW 1550 Alder St. N.W.
Ephrata, WA
Ph: (509) 754-4624 ex.13.
Fax: (509) 754-5257
Email: verhepmv@dfw.wa.gov
Form Submitter
All Assigned Contacts
Ted Nelson WDFW 600 Capitol Way N.
Olympia, WA. 98501
Ph: (360) 902-2401
Fax: (360) 902-2941
Email: nelsontfn@dfw.wa.gov
Administrative Contact
Karen Southwell WDFW 600 Capitol Way N.
Oylmpia, WA 98501
Ph: (360) 664-4993
Fax: (360) 664-3160
Email: southkjs@dfw.wa.gov
Administrative Contact
Patrick Verhey WDFW 1550 Alder St. N.W.
Ephrata, WA
Ph: (509) 754-4624 ex.13.
Fax: (509) 754-5257
Email: verhepmv@dfw.wa.gov
Project Lead

Section 2: Project Location
Sponsor Province: Columbia Plateau ARG Province: No Change
Sponsor Subbasin: Crab ARG Subbasin: No Change
Location(s) at which the action will be implemented
Latitude Longitude Waterbody Location Description County/State Subbasin Primary?
Columbia Plateau Province, Crab Creek Subbasin , Washington Crab No

Section 3: Focal Species
Focal Species:
Primary Secondary Additional Species
All Wildlife
Steelhead Upper Columbia River ESU

Section 4: Past Accomplishments
Past Accomplishments for Each Fiscal Year of This Project This proposal is for funding a new project, and has no past accomplishments.

Section 5: Relationships to Other Projects
Other Current Projects Related to this Project (any funding source)
Funding Source Related ID Related Project Title Relationship
[Funding Source left blank] [no entry] future project proposals The NWPCC relies heavily on the prioritization of projects within the subbasin plan in order to make funding decisions.
BPA 199106100 Swanson Lake Wildlife Mitigati Funding for the wildlife area is mitigation for the construction and operation of Cheif Joseph Dam and Grand Coulee Dam. The NWCC relies heavily on subbasin plans to prioritize funding of projects.
BPA 199502800 Assessment of Fishery Improvem The project goal is to restore the failed recreational fishery for pan fish species (black crappie, bluegill and yellow perch) in Moses Lake. The NWPCC's Columbia River Fish and Wildlife Program funded the project as mitigation for the loss of anadromous salmon and recreational angling above Chief Joseph and Grand Coulee Dams. The NWCC relies heavily on subbasin plans to prioritize funding of projects.
BPA 200102800 Banks Lake Fishery Evaluation The project goal is to conduct a limiting factors analysis to determine the cause of the decline of the kokanee and warmwater recreational fisheries in Banks Lake and to make management recommendations. The project is funded as mitigation for the loss of anadromous salmon and recreational angling above Chief Joseph and Grand Coulee Dams. The NWPCC relies heavily on subbasin plans to prioritize funding of projects.
BPA 200103000 Sharp Tailed Grouse Habitat The Sharp Tailed Grouse Habitat Project addresses elements of the Crab Creek Subbasin Plan.
BPA 200205100 Sub Basin Planning The goal of this project is to complete the Crab Creek Subbasin Plan. The NWCC relies heavily on subbasin plans to prioritize funding of projects.
BPA 200600300 Desert Wildlife Area O&M The wildlife area fulfills offsite mitigation requirements due to the construction of hydroelectric facilities. The NWCC relies heavily on subbasin plans to prioritize funding of projects.

Section 6: Biological Objectives
Biological Objectives of this Proposed Project
Biological Objective Full Description Associated Subbasin Plan Strategy Page Nos
Key ISRP Comments The original Crab Creek Subbasin Plan was inadequately funded and had little time to provide the council with a completed subbasin plan. As a result the ISRP made several comments. It should be acknowledged that funding is not available to address all ISRP comments. The project will address key ISRP comments that are within the provided "fix it" budget. Please refer to the narrative for additional detail. Crab [Strategy left blank] [Pg no blank]
Wildlife Assessment The original Crab Creek Subbasin plan had an incomplete wildlife assessment. The wildlife assessment is a critical component in the development of a wildlife management plan. Crab [Strategy left blank] [Pg no blank]
Wildlife Inventory The original Crab Creek Subbasin plan had an incomplete wildlife inventory. The wildlife inventory is a critical component in the development of a wildlife management plan. Crab [Strategy left blank] [Pg no blank]
Wildlife Management Plan The original Crab Creek Subbasin plan had an incomplete wildlife management plan. ESA listed Sharp-tailed Grouse, Sage Grouse, and Pygmy Rabbits will be focal species used in the development of the management plan. The completion of a wildlife management plan is critical to the adoption of the subbasin plan. Crab [Strategy left blank] [Pg no blank]

Section 7: Work Elements
Work Elements and Associated Biological Objectives
Work Element Name Work Element Title Description Start Date End Date Estimated Budget
Other WDFW Indirect costs recievable contract indirect cost 1/22/2007 3/8/2007 $5,778
Biological Objectives Metrics
No Metrics for this Work Element

1: Produce Plan Address Key ISRP Comments Key ISRP comments made on the original Crab Creek Subbasin Plan will be addressed. See Narrative. 1/22/2007 3/2/2007 $6,400
Biological Objectives Metrics
Key ISRP Comments
No Metrics for this Work Element

2: Produce Inventory or Assessment Wildlife Assessment Complete a formal wildlife assessment, using the NWPCC 2001 Technical Guide for Subbasin Planners. 1/22/2007 2/9/2007 $2,400
Biological Objectives Metrics
Wildlife Assessment
No Metrics for this Work Element

3: Produce Inventory or Assessment Wildlife Inventory Complete a formal wildlife inventory, using the NWPCC 2001 Technical Guide for Subbasin Planners. 1/22/2007 2/9/2007 $2,400
Biological Objectives Metrics
Wildlife Inventory
No Metrics for this Work Element

4: Produce Plan Wildlife Management Plan The original Crab Creek Subbasin plan had an incomplete wildlife management plan. A wildlife management plan will be developed using the NWPCC 2001 Technical Guide for Subbasin Planners. 2/9/2007 2/20/2007 $4,800
Biological Objectives Metrics
Wildlife Management Plan
No Metrics for this Work Element

5: Manage and Administer Projects Administration cost Writing the contracts for the consultants, fulfilling the reporting requirements of NWPCC on the progress of the project. 1/16/2007 3/8/2007 $4,000
Biological Objectives Metrics
No Metrics for this Work Element


Section 8: Budget

Itemized Estimated Budget
Item Note FY 2007 Cost FY 2008 Cost FY 2009 Cost
Overhead wdfw indirect cost 28.89% $5,778 $ 0 $ 0
Personnel [blank] $20,000 $ 0 $ 0
Totals $25,778 $ 0 $ 0

Total Estimated FY 2007-2009 Budgets
Total Itemized Budget$25,778
Total Work Element budget$25,778

Cost sharing
Funding Source or Organization Item or Service Provided FY 2007 Est Value ($) FY 2008 Est Value ($) FY 2009 Est Value ($) Cash or in-kind? Status

Section 9: Project Future
Project Future Costs and/or Termination
FY 2010 Est Budget FY 2011 Est Budget Comments
$ 0 $ 0
Future Operations & Maintenance Costs
 
Termination Date Comments
03/09/2007
 
Final Deliverables
A completed Wildlife Inventory, Assessment, and Management Plan, which will augment the original, Crab Creek Subbasin Plan. By addressing key ISRP comments, the original plan will be strengthened. The plan should be suitable for adoption by the NWPCC.

Section 10: Narrative
Document Type Size Date
Fix-it Loop Documents
Documents Originally Submitted with this Proposal
Narrative for proposal 200724300 doc 63 kb 1/6/2006

Part 2 of 2. Reviews of Proposal
Administrative Review Group (ARG) Results
Account Type:
Expense
No changes were made to this proposal


BPA's in lieu Funding Review of new project proposals (August 3, 2006) [Download letter and table]

BPA's in lieu Rating: 1.0
Approx. BPA share of total costs: BPA 100%
Status of Cost Share:
Notes: Subbasin plan fix it


NPCC Final Funding Recommendations (October 23, 2006) [Full NPCC Council Recs]

FY 2007 NPCC Rec
$ 0
FY 2008 NPCC Rec
$ 0
FY 2009 NPCC Rec
$ 0
Total NPCC Rec
$ 0
Budget Type:Expense
Budget Category:ProvinceExpense
Recommendation:Do Not Fund
NPCC Comments:


NPCC Draft Funding Recommendations (September 15, 2006) [Full NPCC Council Recs]

FY 2007 NPCC Rec
$ 0
FY 2008 NPCC Rec
$ 0
FY 2009 NPCC Rec
$ 0
Total NPCC Rec
$ 0
FY 2007 MSRT Rec
$ 0
FY 2008 MSRT Rec
$ 0
FY 2009 MSRT Rec
$ 0
Total MSRT Rec
$ 0
Budget Category:ProvinceExpense
NPCC Comments:
NPCC Staff Comments: No subbasin plan

Local or MSRT Comments: See Washington guidance


Independent Scientific Review Panel Final Review (August 31, 2006) [Download full document]

Recommendation: Not fundable
Comments: The problem addressed in this proposal is that of an inadequate subbasin plan. This appears to be a request for funding to write a proposal and is not applicable for ISRP review. Sufficient information was not provided on methods to scientifically justify this proposal. The response by the sponsors does not change the recommendation. The ISRP maintains its preliminary comments and recommendation of "Not fundable."


Independent Scientific Review Panel Preliminary Review (June 2, 2006) [Download full document]

Recommendation: Not fundable
Comments: The problem addressed in this proposal is that of an inadequate subbasin plan. This appears to be a request for funding to write a proposal and is not applicable for ISRP review. Sufficient information was not provided on methods to scientifically justify this proposal