Part 1 of 2. Administration and Budgeting
|
| Section 1: General Administrative Information |
| Process Information: |
| Date Proposal Submitted & Finalized |
Status |
Form Generator |
| July 14, 2006 |
Finalized |
Patrick Verhey |
| DB Administrator's Note |
[Per conversation with Patrick Verhey on 3/17/2006, Itemized budget total should be $20,000 rather than $5,778. - DBA] |
|
|
| Proposal Type: |
New |
| Proposal Number: |
200724300 |
| Proposal Name: |
Crab Creek Subbasin Plan 2007 |
| Agency, Institution or Organization: |
Washington Department of Fish and Wildlife (WDFW) |
| Short Description: |
Project will provide a more complete wildlife section (assessment, inventory, and management plan) and address key ISRP comments on the original Crab Creek Subbasin Plan.The goal of the project is the adoption of the Crab Creek Subbasin Plan by the NWPCC. |
| Information Transfer: |
The information will be used to update the current Crab Creek Subbasin Plan in order for the plan to be adopted by NWPCC. The Crab Creek Subbasin Plan will be used to prioritize projects that lead to the recovery of ESA listed species. ESA listed species within the subbasin include Steelhead, Sharp-tailed Grouse, Sage Grouse, and Pygmy Rabbits. The plan will be posted on the NWPCC internet site. |
| |
| Project Proposal Contacts |
| Contact |
Organization |
Address |
Phone/Email |
Roles |
Notes |
|
Form Submitter |
| Patrick Verhey |
WDFW |
1550 Alder St. N.W.
Ephrata, WA |
Ph: (509) 754-4624 ex.13.
Fax: (509) 754-5257
Email: verhepmv@dfw.wa.gov |
Form Submitter |
|
|
All Assigned Contacts |
| Ted Nelson |
WDFW |
600 Capitol Way N.
Olympia, WA. 98501 |
Ph: (360) 902-2401
Fax: (360) 902-2941
Email: nelsontfn@dfw.wa.gov |
Administrative Contact
|
|
| Karen Southwell |
WDFW |
600 Capitol Way N.
Oylmpia, WA 98501 |
Ph: (360) 664-4993
Fax: (360) 664-3160
Email: southkjs@dfw.wa.gov |
Administrative Contact
|
|
| Patrick Verhey |
WDFW |
1550 Alder St. N.W.
Ephrata, WA |
Ph: (509) 754-4624 ex.13.
Fax: (509) 754-5257
Email: verhepmv@dfw.wa.gov |
Project Lead
|
|
|
|
| Section 2: Project Location |
| Sponsor Province: |
Columbia Plateau |
ARG Province: |
No Change |
| Sponsor Subbasin: |
Crab |
ARG Subbasin: |
No Change |
| Location(s) at which the action will be implemented |
| Latitude |
Longitude |
Waterbody |
Location Description |
County/State |
Subbasin |
Primary? |
|
|
|
Columbia Plateau Province, Crab Creek Subbasin |
, Washington |
Crab |
No |
|
|
| Section 3: Focal Species |
| Focal Species: |
| Primary |
Secondary |
Additional Species |
All Wildlife
|
Steelhead Upper Columbia River ESU
|
|
|
|
| Section 4: Past Accomplishments |
| Past Accomplishments for Each Fiscal Year of This Project |
This proposal is for funding a new project, and has no past accomplishments.
|
|
| Section 5: Relationships to Other Projects |
| Other Current Projects Related to this Project (any funding source) |
| Funding Source |
Related ID |
Related Project Title |
Relationship |
| [Funding Source left blank] |
[no entry] |
future project proposals |
The NWPCC relies heavily on the prioritization of projects within the subbasin plan in order to make funding decisions. |
| BPA |
199106100 |
Swanson Lake Wildlife Mitigati |
Funding for the wildlife area is mitigation for the construction and operation of Cheif Joseph Dam and Grand Coulee Dam. The NWCC relies heavily on subbasin plans to prioritize funding of projects. |
| BPA |
199502800 |
Assessment of Fishery Improvem |
The project goal is to restore the failed recreational fishery for pan fish species (black crappie, bluegill and yellow perch) in Moses Lake. The NWPCC's Columbia River Fish and Wildlife Program funded the project as mitigation for the loss of anadromous salmon and recreational angling above Chief Joseph and Grand Coulee Dams. The NWCC relies heavily on subbasin plans to prioritize funding of projects. |
| BPA |
200102800 |
Banks Lake Fishery Evaluation |
The project goal is to conduct a limiting factors analysis to determine the cause of the decline of the kokanee and warmwater recreational fisheries in Banks Lake and to make management recommendations. The project is funded as mitigation for the loss of anadromous salmon and recreational angling above Chief Joseph and Grand Coulee Dams. The NWPCC relies heavily on subbasin plans to prioritize funding of projects. |
| BPA |
200103000 |
Sharp Tailed Grouse Habitat |
The Sharp Tailed Grouse Habitat Project addresses elements of the Crab Creek Subbasin Plan. |
| BPA |
200205100 |
Sub Basin Planning |
The goal of this project is to complete the Crab Creek Subbasin Plan. The NWCC relies heavily on subbasin plans to prioritize funding of projects. |
| BPA |
200600300 |
Desert Wildlife Area O&M |
The wildlife area fulfills offsite mitigation requirements due to the construction of hydroelectric facilities. The NWCC relies heavily on subbasin plans to prioritize funding of projects. |
|
|
| Section 6: Biological Objectives |
| Biological Objectives of this Proposed Project |
| Biological Objective |
Full Description |
Associated Subbasin Plan |
Strategy |
Page Nos |
| Key ISRP Comments |
The original Crab Creek Subbasin Plan was inadequately funded and had little time to provide the council with a completed subbasin plan. As a result the ISRP made several comments. It should be acknowledged that funding is not available to address all ISRP comments. The project will address key ISRP comments that are within the provided "fix it" budget. Please refer to the narrative for additional detail. |
Crab |
[Strategy left blank] |
[Pg no blank] |
| Wildlife Assessment |
The original Crab Creek Subbasin plan had an incomplete wildlife assessment. The wildlife assessment is a critical component in the development of a wildlife management plan. |
Crab |
[Strategy left blank] |
[Pg no blank] |
| Wildlife Inventory |
The original Crab Creek Subbasin plan had an incomplete wildlife inventory. The wildlife inventory is a critical component in the development of a wildlife management plan. |
Crab |
[Strategy left blank] |
[Pg no blank] |
| Wildlife Management Plan |
The original Crab Creek Subbasin plan had an incomplete wildlife management plan. ESA listed Sharp-tailed Grouse, Sage Grouse, and Pygmy Rabbits will be focal species used in the development of the management plan. The completion of a wildlife management plan is critical to the adoption of the subbasin plan. |
Crab |
[Strategy left blank] |
[Pg no blank] |
|
|
| Section 7: Work Elements |
| Work Elements and Associated Biological Objectives |
| Work Element Name |
Work Element Title |
Description |
Start Date |
End Date |
Estimated Budget |
| Other |
WDFW Indirect costs |
recievable contract indirect cost |
1/22/2007 |
3/8/2007 |
$5,778 |
| Biological Objectives |
Metrics |
|
No Metrics for this Work Element |
|
| 1: Produce Plan |
Address Key ISRP Comments |
Key ISRP comments made on the original Crab Creek Subbasin Plan will be addressed. See Narrative. |
1/22/2007 |
3/2/2007 |
$6,400 |
| Biological Objectives |
Metrics |
Key ISRP Comments
|
No Metrics for this Work Element |
|
| 2: Produce Inventory or Assessment |
Wildlife Assessment |
Complete a formal wildlife assessment, using the NWPCC 2001 Technical Guide for Subbasin Planners. |
1/22/2007 |
2/9/2007 |
$2,400 |
| Biological Objectives |
Metrics |
Wildlife Assessment
|
No Metrics for this Work Element |
|
| 3: Produce Inventory or Assessment |
Wildlife Inventory |
Complete a formal wildlife inventory, using the NWPCC 2001 Technical Guide for Subbasin Planners. |
1/22/2007 |
2/9/2007 |
$2,400 |
| Biological Objectives |
Metrics |
Wildlife Inventory
|
No Metrics for this Work Element |
|
| 4: Produce Plan |
Wildlife Management Plan |
The original Crab Creek Subbasin plan had an incomplete wildlife management plan. A wildlife management plan will be developed using the NWPCC 2001 Technical Guide for Subbasin Planners. |
2/9/2007 |
2/20/2007 |
$4,800 |
| Biological Objectives |
Metrics |
Wildlife Management Plan
|
No Metrics for this Work Element |
|
| 5: Manage and Administer Projects |
Administration cost |
Writing the contracts for the consultants, fulfilling the reporting requirements of NWPCC on the progress of the project. |
1/16/2007 |
3/8/2007 |
$4,000 |
| Biological Objectives |
Metrics |
|
No Metrics for this Work Element |
|
|
|
| Section 8: Budget |
|
| Itemized Estimated Budget |
| Item |
Note |
FY 2007 Cost |
FY 2008 Cost |
FY 2009 Cost |
| Overhead |
wdfw indirect cost 28.89% |
$5,778 |
$ 0 |
$ 0 |
| Personnel |
[blank] |
$20,000 |
$ 0 |
$ 0 |
| Totals |
$25,778 |
$ 0 |
$ 0 |
|
|
| Total Estimated FY 2007-2009 Budgets |
| Total Itemized Budget | $25,778 |
| Total Work Element budget | $25,778 |
|
|
| Cost sharing |
| Funding Source or Organization |
Item or Service Provided |
FY 2007 Est Value ($) |
FY 2008 Est Value ($) |
FY 2009 Est Value ($) |
Cash or in-kind? |
Status |
|
|
| Section 9: Project Future |
| Project Future Costs and/or Termination |
| FY 2010 Est Budget |
FY 2011 Est Budget |
Comments |
| $ 0 |
$ 0 |
|
| Future Operations & Maintenance Costs |
|
| |
| Termination Date |
Comments |
| 03/09/2007 |
|
| |
| Final Deliverables |
| A completed Wildlife Inventory, Assessment, and Management Plan, which will augment the original, Crab Creek Subbasin Plan. By addressing key ISRP comments, the original plan will be strengthened. The plan should be suitable for adoption by the NWPCC. |
|
|
| Section 10: Narrative |
|
|
|
Part 2 of 2. Reviews of Proposal
|
| Administrative Review Group (ARG) Results |
Account Type:
Expense |
No changes were made to this proposal |
BPA's in lieu Funding Review of new project proposals (August 3, 2006)
[Download letter and table]
|
BPA's in lieu Rating: 1.0
Approx. BPA share of total costs: BPA 100%
Status of Cost Share:
|
| Notes: Subbasin plan fix it |
NPCC Final Funding Recommendations (October 23, 2006)
[Full NPCC Council Recs]
|
FY 2007 NPCC Rec $ 0 |
FY 2008 NPCC Rec $ 0 |
FY 2009 NPCC Rec $ 0 |
Total NPCC Rec $ 0 |
| Budget Type: | Expense |
| Budget Category: | ProvinceExpense |
| Recommendation: | Do Not Fund
|
| NPCC Comments: |
NPCC Draft Funding Recommendations (September 15, 2006)
[Full NPCC Council Recs]
|
FY 2007 NPCC Rec $ 0 |
FY 2008 NPCC Rec $ 0 |
FY 2009 NPCC Rec $ 0 |
Total NPCC Rec $ 0 |
FY 2007 MSRT Rec $ 0 |
FY 2008 MSRT Rec $ 0 |
FY 2009 MSRT Rec $ 0 |
Total MSRT Rec $ 0 |
| Budget Category: | ProvinceExpense |
| NPCC Comments: |
| NPCC Staff Comments: No subbasin plan
Local or MSRT Comments: See Washington guidance
|
Independent Scientific Review Panel Final Review (August 31, 2006)
[Download full document]
|
| Recommendation: Not fundable
|
| Comments: The problem addressed in this proposal is that of an inadequate subbasin plan. This appears to be a request for funding to write a proposal and is not applicable for ISRP review. Sufficient information was not provided on methods to scientifically justify this proposal. The response by the sponsors does not change the recommendation. The ISRP maintains its preliminary comments and recommendation of "Not fundable." |
Independent Scientific Review Panel Preliminary Review (June 2, 2006)
[Download full document]
|
| Recommendation: Not fundable
|
| Comments: The problem addressed in this proposal is that of an inadequate subbasin plan. This appears to be a request for funding to write a proposal and is not applicable for ISRP review. Sufficient information was not provided on methods to scientifically justify this proposal |
Maintained by the Columbia Basin Fish & Wildlife Authority. Please direct comments or questions to the webmaster.